A. Scope & progress of Contract from Km 19 to Km 47 and Bridge works from Km 19 to Km 67
Item | Scope of work | Upto date Physical progress | Remarks |
Earthwork (Lakh cum) | 28.99 | 18.22 | |
Minor Bridges (Nos) (Including ROB and RUB) |
69 | Completed – 26 Work in Progress – 12 |
B. Scope & progress of Contract from Km 0 to 19 and Km 47 to Km 97 and Blanketing works in entire length of 104 route Km between Budhapank to Baghuapal
Item | Scope of work | Upto date Physical progress | Remarks |
Earthwork (Lakh cum) | 35 | 16.27 – Earth Filling 15.01 – Earth Cutting |
|
Minor Bridges (Nos) Including ROB and RUB |
112 | Completed – 23 Work in Progress – 23 |