A. Bridge on river Brahmani and on Rengali canal.
Status of Bridge Works up to 31.05.2017 | ||
---|---|---|
Major Bridge | Location | Progress Achieved |
Bridge No 12 | River Brahmani | 92% |
Bridge No 29 | Rengali Canal | 89% |
Bridge No 41 | Rengali Canal | 80% |
B. Execution of bridges between Budhapank to Baghuapal
Total Bridges | Physical Progress |
---|---|
28 nos | Completed – 1 Work in progress – 5 |